Financial Status
Below is a quick report of the history of the donations requested, received and the use of the funds.
| 2026 | |
|---|---|
| Final Renovation Costs (Revised 2025) | 3.0 Million € |
| Funds available by the end of 2025 (after all expenses) | (0.76) Million € |
| Donations received as of the end of Oct. 2026 | (1.15) Million € |
| Professional services already paid in 2025 | (0.07) Million € |
| Donations committed locally by the church in Stuttgart | (0.10) Million € |
| Amount still needed to completed the project | 0.92 Million € |
| 2025 | |
|---|---|
| Original Renovation cost estimates (2023) | 1.9 Million € |
| Increased in costs due to fire protection, opening up the basement, and inflation in labor and materials | 1,1 Million € |
| Revised final renovation cost | 3.0 Million € |
| Funds available by the end of 2024 | 0.91 Million € |
| Costs paid to obtain change of use and renovation permits, architect and other permit related professional services in 2025 | 0.15 Million € |
| Remaining Funds | 0.76 Million € |
| 2023 | |
|---|---|
| Total Donations received (Actual) | 2.47 Million € |
| Amount paid to purchase the property and fees | (1.56) Million € |
| Remaining Funds | 0.91 Million € |
| Oct 2022 | |
|---|---|
| Property Purchase price | 1.56 Million € |
| Estimated Renovation Costs included car parks | 1.90 Million € |
| Announcement for property purchase and Phase 1 renovation (1.56 MIl€ plus 0.50 Mil €) | 2.06 Million € |
| Donation received and pledged | 1.35 Million € |